Project Management

Project Management

49 questions · Fundamental Engineering

Practice

In project management, which of the following is the subject group with Purpose 1 and Purpose 2?

Purpose 1:To clarify the objectives, deliverables, requirements, and boundaries of the projectPurpose 2:To maximize positive impact and minimize negative impact to the project occurring as a result of the changes in project objectives and deliverables

The functional size of a new system was estimated to be 500 function points (FPs). Apart from development, the project requires 10 person-months in total for installation of the system and education of developers. Additionally project management requires 10% of the total person-months of development, installation, and education. How many person-months are required in total for this project? Here, the productivity in development is 10 FPs per person-month.

Eight (8) activities and milestones of a project are shown in the arrow diagram below. Which of the following is the critical path of this project?

A15D10E15B10C15F15G5H10Legend:Activity nameNumber of daysrequiredDummy

Based on the requirements gathered, the cost of a software project under normal conditions is estimated at $70,000. In case of smooth project implementation, some activities are not required and the estimated cost is reduced to $50,000; however, in the worst-case scenario, additional tasks are required and the cost increases to $120,000. What is the expected cost of the project (in dollars) that is calculated by using the three-point estimate in the beta distribution, also known as PERT?

Which of the following is an appropriate explanation of earned value in project management?

Which of the following is the method of estimation in the COCOMO model in software estimation?

Which of the following is an appropriate purpose for using a Work Breakdown Structure (WBS) in a software development project?

Which of the following is an appropriate explanation concerning the scope creep in project scope management?

The activities and milestones of a project are shown in the arrow diagram below. Which of the following is an appropriate description of the project if the duration of activity B is increased by 5 days?

A10B5C10D25E10F20G15H15LegendsActivity nameNumber ofdays requiredDummy activity

What is the Cost Performance Index (CPI) of the project under the conditions listed below?

Project Budget (BAC)100,000 dollars
Project Duration4 months
Elapsed Time1 month
Actual Cost (AC)20,000 dollars
Project ProgressAs planned

The ten members of a project team hold meetings with each other with the conditions below. If two (2) members are to be added to the team, how many additional meetings will be held compared to if there were ten members?

[Conditions]

  • •Meetings are held one-on-one.
  • •Each member holds one meeting with every other member.

When the number of programs composing the system and the number of person-days required for coding per program are as shown in the table below, what is the minimum number of staff members required to develop the system in 95 days? Here, in addition to coding, the activities of design and testing are also necessary to develop the system, and those activities require eight times as many person-days as coding.

 Number of programsNumber of person-days requiredfor coding per program
Input processing201
Output processing103
Calculation processing59

Which of the following is a critical path of the project activities shown in the arrow diagram below?

A2B3C3D1E1F3G4H3I2J2K2L3
Legend:Activity nameNumber of daysrequired

Which of the following is an appropriate description of the stakeholders involved in a project?

In project management, which of the following is the subject group that includes processes having Purpose 1 and those having Purpose 2?

[Purposes]Purpose 1:To clarify the objectives, deliverables, requirements, and boundaries of the projectPurpose 2:To maximize the positive impacts to the project and minimize the negative impacts, both of which occur as a result of changes in the objectives and deliverables of the project

A project was planned to be completed in six months. After six months, the project is behind schedule. The actual cost of Activity A is $100,000. The planned value of Activity A is $80,000. Activity A is only 75% complete. What is the schedule performance index and cost performance index of the project?

OptionSchedule performance indexCost performance index

Which of the following is an appropriate explanation of the Function Point method for creating an estimate for software development?

A project consisting of several activities has a single critical path. Which of the following is an appropriate description of critical path activities for the project?

Which of the following is an appropriate description of the Responsibility Assignment Matrix that is used for project human resource management?

Which of the following is an appropriate purpose for using a WBS (work breakdown structure) in a software development project?

Which of the following is an appropriate description for group decision-making techniques used in the estimation process of an activity duration?

Which of the following is an appropriate tool that implements a deliverable-oriented decomposition of a project into smaller components?

Which of the following is an appropriate description of scope management?

When the triangular distribution formula in the three-point estimation technique is used, which of the following is the expected duration in days required for an activity? The estimates are as shown below.

Conditions – Estimates for the duration of the activity

  Case 1: Two (2) days – if an experienced employee is assigned to this activity

  Case 2: Four (4) days – if an average employee is assigned to this activity

  Case 3: Twelve (12) days – if an inexperienced employee is assigned to this activity

The arrow diagram below shows a project’s activities and milestones. Which of the following is the minimum project completion time in days?

A3B8E11F7G8H6I4C4D7LegendActivitynameNumber ofdays required: Dummy activity

Based on the definition of project management process groups in ISO 21500, which of the following is an activity that is to be implemented in the planning process group among the project management processes?

In project time management, which of the following descriptions is appropriate for “slack time”?

When the duration for painting a house is estimated, which of the following is an appropriate technique that estimates the duration on the basis of the actual duration of a similar painting job in the past of the same house or other historical data from similar work?

In system development, when the relationship between person-months and the duration (months) is represented in the approximate expression shown below, and the total person-month is 4096, how many months does it take?

Duration = 2.5 × person-months1/3

Which of the following is one of the major responsibilities of a project manager?

A project is planned to complete in 12 months and the budget for the completion of the project is $100,000. After six months, it is found that $60,000 was spent, but only 40% of the work has been completed. If the Cost Performance Index (CPI) is not changed, what is the estimated amount (in dollars) required to complete the remaining tasks of the project?

In project time management, which of the following is the amount of time that the start of a successor activity requires to be delayed after the finish of a predecessor activity?

The activities and nodes of a project are shown in the arrow diagram below. Which of the following is the effect of extending the duration of activity C by 3 days?

A3B4D6C5F7E6G5H1
Legend:NodeActivityActivity nameNumber of days requiredDummy activity

According to PMBOK, which of the following is the description of scope creep?

A project with a development period of 10 months and the person−hours required for development as 200 person-months is planned. Which of the following is the number of staff members required during the peak time based on the distribution sheet shown below? Here, the number of staff members does not change from the start till the end of every process.

ProcessnameItemRequirementsdefinitionDesignDevelopment/TestSystem testAllocation ofperson-hours (%)Allocation of timeperiod (%)163342920304010

Which of the following is an explanation of the function point method?

According to the 6th edition of the PMBOK Guide, which of the following is an activity for the planning process group in project resource management?

The activities and milestones of a project are shown in the arrow diagram below. Which of the following is an impact of reducing the duration of activity, D, by 3 days?

B5A6C7D5E4F6
Legend:Activity nameNumber ofdays requiredDummy activity

Screens are created for a system that is composed of a total of 100 screens. The breakdown of the 100 screens classified on the basis of size and complexity is shown below.

Number of screens with a “Small” size and “Low” complexity: 30

Number of screens with a “Medium” size and “Medium” complexity: 40

Number of screens with a “Large” size and “Medium” complexity: 20

Number of screens with a “Large” size and “High” complexity: 10

If the total number of person-days for creating all screens is estimated by using the number of person-days for creation shown in the table below, how many person-days are required? Here, a review and revision of all the screens requires five (5) person-days, and project management requires 20% of the total person-days, including the person-days for review and revision.

Number of person-days for creating each screen

Unit: Person-dayComplexitySizeLowMediumHighSmall0.40.60.8Medium0.60.91.0Large0.81.01.2

Which of the following is the technique for estimating activity durations where past information is statistically analyzed and various coefficients are determined?

Which of the following is an appropriate explanation of the PERT diagram as shown in the figure below?

A2B4C2F4D2G4H5
LegendActivity nameNumber of daysrequired

By using the triangular distribution formula of the three-point estimation technique, which of the following is the expected duration (in days) required for an activity? The estimations are as shown below.

Conditions – Estimations for the activity duration

  Case 1: Two (2) days. If an experienced employee is assigned for this activity.

  Case 2: Four (4) days. If a general employee is assigned for this activity.

  Case3: Twelve (12) days. If an unexperienced employee is assigned for this activity.

Which of the following is an appropriate cost estimation technique that estimates the cost of an activity or project using the historical data from a similar project?

Which of the following is an appropriate description for group decision-making techniques used in an estimate activity durations process?

Which of the following is an appropriate description of the activities on the critical path of a project?

Which of the following is an appropriate cost estimation technique that uses parametric models to create an objective estimate based on each element size and the complexity of the system (e.g., number of input files, screens, etc.) to be built?

Which of the following is the structure that illustrates the relationship between project activity and the units of project that will perform those activities?

According to the PMBOK Guide – Fifth Edition, which of the following is an appropriate definition of a project stakeholder?

Which of the following is an appropriate explanation of the Function Point method that is used for system development estimation?