ITPEC FE Subject A April 2024 Question 42

What is the Cost Performance Index (CPI) of the project under the conditions listed below?

Project Budget (BAC)100,000 dollars
Project Duration4 months
Elapsed Time1 month
Actual Cost (AC)20,000 dollars
Project ProgressAs planned

Explanation

1.25 — progress as planned means the earned value equals the planned value, which is then divided by the actual cost.

  • •Planned value after 1 of 4 months: 100,000 × 1 ÷ 4 = 25,000 dollars
  • •Earned value: progress is as planned, so EV = PV = 25,000 dollars
  • •CPI: EV ÷ AC = 25,000 ÷ 20,000 = 1.25

A CPI above 1 means the work done so far cost less than its budget.

Answer (d)

Why not others:

  • •(a) 0.25 — 25,000 ÷ 100,000, EV over the total budget: the share of work completed, not cost efficiency
  • •(b) 0.8 — 20,000 ÷ 25,000, the formula inverted as AC ÷ EV
  • •(c) 1.0 — the schedule performance index, EV ÷ PV, which is 1 because progress is as planned; the cost index compares EV with AC

Key rule: CPI = EV ÷ AC and SPI = EV ÷ PV; above 1 is favourable for both, and "as planned" settles only the SPI.

Project Management · AI-written, may contain errors

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.