ITPEC FE Subject A April 2024 Question 42
Topic: Project Management
What is the Cost Performance Index (CPI) of the project under the conditions listed below?
Explanation
1.25 — progress as planned means the earned value equals the planned value, which is then divided by the actual cost.
- •Planned value after 1 of 4 months: 100,000 × 1 ÷ 4 = 25,000 dollars
- •Earned value: progress is as planned, so EV = PV = 25,000 dollars
- •CPI: EV ÷ AC = 25,000 ÷ 20,000 = 1.25
A CPI above 1 means the work done so far cost less than its budget.
Answer (d)
Why not others:
- •(a) 0.25 — 25,000 ÷ 100,000, EV over the total budget: the share of work completed, not cost efficiency
- •(b) 0.8 — 20,000 ÷ 25,000, the formula inverted as AC ÷ EV
- •(c) 1.0 — the schedule performance index, EV ÷ PV, which is 1 because progress is as planned; the cost index compares EV with AC
Key rule: CPI = EV ÷ AC and SPI = EV ÷ PV; above 1 is favourable for both, and "as planned" settles only the SPI.