ITPEC FE Morning April 2019 Question 51

Source exam: ITPEC FE Morning April 2019Topic: Project Management

ITPEC FE Morning April 2019 — Question 51 of 80

Critical Path & PERT Diagram — Evaluating the effect of removing or delaying activities on project duration.

All paths from start to end:
- A→C→G: 2+2+4 = 8

- B→F→G: 4+4+4 = 12 (critical path)

- B→D→H: 4+2+5 = 11

The critical path is B→F→G = 12 days.

The correct answer is c): When activity F becomes unnecessary, the project will end 1 day earlier.

Without F, the remaining paths are A→C→G (8) and B→D→H (11). The new critical path becomes 11 days — a reduction of exactly 1 day from the original 12.

Why not the others:
- a) A–C–G = 8 days, not the critical path

- b) The project requires 12 days (not 11)

- d) A 2-day delay on H makes B→D→H = 13, changing the project from 12 to 13 — only a 1-day delay, not 2

Key rule: Removing an activity from the critical path shortens the project only by the difference between the old and new critical path lengths. A delay on a non-critical activity causes project delay only if it exceeds that activity's float.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.