PMBOK 6th Edition — Resource Management process groups — identify which processes belong to Planning vs Executing vs Monitoring & Controlling.
Project Resource Management has 6 processes across 3 process groups:
- •Planning: Plan Resource Management, Estimate Activity Resources
- •Executing: Acquire Resources, Develop Project Team, Manage Project Team
- •Monitoring & Controlling: Control Resources
Why not others:
- (a) Acquire resources — belongs to the Executing process group
- (b) Control resources — belongs to Monitoring & Controlling
- (c) Develop project team — belongs to the Executing process group
Key rule: Planning processes only plan and estimate — no hands-on action yet. Acquiring, developing, and managing happen during Executing.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.