ITPEC FE Morning April 2019 Question 52

Topic: Project ManagementAlso asked in April 2022

By using the triangular distribution formula of the three-point estimation technique, which of the following is the expected duration (in days) required for an activity? The estimations are as shown below.

Conditions – Estimations for the activity duration

  Case 1: Two (2) days. If an experienced employee is assigned for this activity.

  Case 2: Four (4) days. If a general employee is assigned for this activity.

  Case3: Twelve (12) days. If an unexperienced employee is assigned for this activity.

Explanation

6 days — the triangular distribution weights the three estimates equally.

  • •Optimistic O = 2, most likely M = 4, pessimistic P = 12
  • •Expected duration: E = (O + M + P) ÷ 3 = (2 + 4 + 12) ÷ 3 = 18 ÷ 3 = 6

Answer (c)

Why not others:

  • •(a) 4 — the most likely estimate alone, ignoring the other two
  • •(b) 5 — the beta (PERT) formula (O + 4M + P) ÷ 6 = (2 + 16 + 12) ÷ 6 = 5, not the triangular one the question asks for
  • •(d) 7 — (2 + 12) ÷ 2, the midpoint of the optimistic and pessimistic estimates, leaving out the most likely one

Key rule: The triangular estimate divides the plain sum by 3, while the beta (PERT) estimate weights the most likely value by 4 and divides by 6; check which distribution the question names.