ITPEC FE Morning April 2019 Question 52

Source exam: ITPEC FE Morning April 2019Topic: Project Management

ITPEC FE Morning April 2019 — Question 52 of 80

Three-Point Estimation (Triangular Distribution) — calculating expected duration from three scenario estimates

The triangular distribution formula:

E = (O + M + P) / 3

  • O (Optimistic) = 2 days (experienced employee)
  • M (Most Likely) = 4 days (general employee)
  • P (Pessimistic) = 12 days (unexperienced employee)

E = (2 + 4 + 12) / 3 = 18 / 3 = 6

Answer: c) 6

Why not others:
- a) 4 — just the most likely value, not the average of all three

- b) 5 — this would come from the PERT/Beta formula (O + 4M + P) / 6, but the question specifies triangular distribution

- d) 7 — does not match any standard formula with these inputs

Key rule: Two three-point estimation formulas exist: Triangular = (O + M + P) / 3 (simple average), PERT/Beta = (O + 4M + P) / 6 (weighted toward most likely). Read the question carefully to know which one to apply.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.