ITPEC FE Morning October 2022 Question 51
ITPEC FE Morning October 2022 — Question 51 of 80
Critical Path Activities — on a critical path, early start equals late start for every activity.
Critical path = longest path through the project network. Activities on it have zero total float.
- •Total float =
late start − early start(orlate finish − early finish) - •If float =
0→ early start = late start, early finish = late finish - •Any delay on a critical path activity delays the entire project
Why not others:
- (a) Can be performed in parallel — possible but not a defining property of critical path
- (b) Non-zero total float — wrong, critical path activities have zero float
- (d) Longest duration activity is on critical path — critical path is the longest path (chain), not the longest single activity
Key rule: Critical path activity → total float = 0 → no schedule flexibility → ES = LS, EF = LF.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.