ITPEC FE Subject A October 2025 Question 41
Eight (8) activities and milestones of a project are shown in the arrow diagram below. Which of the following is the critical path of this project?
Explanation
A → C → E → H, 55 days — the critical path is the longest route from start to finish, and the dummy makes E wait for C.
The dummy takes 0 days but runs from the milestone after B and C to the start of E, so E cannot start until C is done. Every route from start to finish:
The same result by earliest times: the lower-left milestone is reached at day 30 (A then C beats B's 10), E starts at day 30 (the dummy beats D's day 25), and the finish is day 30 + 15 + 10 = 55.
Answer (a)
Why not others:
- •(b) A, C, F, G — 50 days: after C, the lower branch F → G takes 20 days, less than dummy → E → H at 25
- •(c) B, E, H — 35 days: starting with B reaches the lower-left milestone at day 10 instead of day 30 via A and C
- •(d) B, F, G — 30 days, the shortest route of all
Key rule: At each milestone take the latest of the incoming arrows (a dummy counts 0 days); the arrows that set those maxima form the critical path.
Project Management · AI-written, may contain errors