ITPEC FE Subject A October 2025 Question 41

Source exam: ITPEC FE Subject A October 2025Topic: Project Management

ITPEC FE Subject A October 2025 — Question 41 of 60

The critical path is the longest path through the network. Dummy activities (dashed arrows) have duration 0 but represent dependencies.

All paths from start to finish:

PathCalculationTotal
A → C → E → H15 + 0 + 15 + 1040
A → C → F → G15 + 0 + 15 + 535
B → E → H10 + 15 + 1035
B → F → G10 + 15 + 530

The longest path is A → C → E → H = 40 days.

Why not others:
- (b) A, C, F, G — 35 days, shorter because G = 5 instead of H = 10

- (c) B, E, H — 35 days, shorter because B = 10 vs A + C = 15

- (d) B, F, G — 30 days, the shortest path

Key rule: Critical path = longest path in the network; dummy activities count as 0 duration but enforce predecessor relationships.

AI-generated — may contain errors