ITPEC FE Morning April 2018 Question 52

Source exam: ITPEC FE Morning April 2018Topic: Project Management

ITPEC FE Morning April 2018 — Question 52 of 80

Responsibility Assignment Matrix (RAM) — maps project activities to responsible organizational units.

RAM (also called RACI matrix) is a table where:
- Rows = project activities (tasks, work packages)

- Columns = organizational units (teams, roles, individuals)

- Cells = responsibility type (e.g., Responsible, Accountable, Consulted, Informed)

Key phrase: "relationship between project activity and the units of project" → RAM.

Why not others:
- (a) OBS (Organizational Breakdown Structure) — hierarchy of project organizational units only, no link to activities

- (b) PBS (Product Breakdown Structure) — hierarchy of product components/deliverables, no link to who performs work

- (d) WBS (Work Breakdown Structure) — hierarchy of project work/tasks, no link to who is responsible

Memory tip: RAM = Roles Assigned to activities Matrix — the only one that connects who to what.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.