ITPEC FE Subject A April 2026 Question 41
ITPEC FE Subject A April 2026 — Question 41 of 60
Scope — the subject group that defines what the project includes and controls changes to it.
- •Purpose 1 — clarifying objectives, deliverables, requirements and boundaries is scope definition
- •Purpose 2 — handling the impact of changes to those objectives and deliverables is scope change control
Both statements are about the same thing: the agreed content of the project.
Answer (d)
Why not others:
- (c) Risk — the tempting choice, because "maximize positive and minimize negative impact" is the language of risk management; but here the impact arises from changes to objectives and deliverables, which is scope control, not uncertain future events
- (a) Communication — getting the right information to stakeholders at the right time
- (b) Procurement — acquiring goods and services from outside the organisation
Key rule: Identify what the impact comes from. Uncertain events that may or may not occur belong to risk; changes to agreed deliverables belong to scope.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.