ITPEC FE Morning October 2018 Question 52

Source exam: ITPEC FE Morning October 2018Topic: Project Management

ITPEC FE Morning October 2018 — Question 52 of 80

Group Decision-Making Techniques — identify team-based estimation approaches in project scheduling.

The question asks which option describes group decision-making techniques for estimating activity durations.

Answer: (c)

Group decision-making techniques are team-based approaches used to improve estimate accuracy and build team commitment:
- Brainstorming — open idea generation

- Delphi technique — anonymous expert rounds converging on consensus

- Nominal group technique — structured voting after individual input

Why not others:
- (a) — describes expert judgment (experts using historical data to provide estimates)

- (b) — describes reserve analysis (adding contingency reserves / buffers for schedule uncertainty)

- (d) — describes parametric estimating (using statistical relationships between historical data and variables to calculate cost, budget, or duration)

Key rule: "Team-based approaches" + names like Delphi, brainstorming, nominal group = group decision-making techniques.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.