ITPEC FE Subject A October 2025 Question 42

Based on the requirements gathered, the cost of a software project under normal conditions is estimated at $70,000. In case of smooth project implementation, some activities are not required and the estimated cost is reduced to $50,000; however, in the worst-case scenario, additional tasks are required and the cost increases to $120,000. What is the expected cost of the project (in dollars) that is calculated by using the three-point estimate in the beta distribution, also known as PERT?

Explanation

$75,000 — PERT weights the most likely estimate four times against the optimistic and pessimistic ones.

  • •Optimistic O = 50,000, most likely M = 70,000, pessimistic P = 120,000
  • •Expected value: E = (O + 4M + P) ÷ 6
  • •E = (50,000 + 4 × 70,000 + 120,000) ÷ 6 = 450,000 ÷ 6 = 75,000

Answer (b)

Why not others:

  • •(a) 70,000 — the most likely estimate alone, without the optimistic and pessimistic cases
  • •(c) 80,000 — the plain average (50,000 + 70,000 + 120,000) ÷ 3, which gives the most likely value the same weight as the extremes
  • •(d) 85,000 — the midpoint of the optimistic and pessimistic costs, (50,000 + 120,000) ÷ 2, which ignores the most likely estimate

Key rule: A PERT three-point estimate is (O + 4M + P) ÷ 6, and its standard deviation is (P − O) ÷ 6.

Project Management · AI-written, may contain errors

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.