ITPEC FE Subject A April 2025 Question 41
Which of the following is an appropriate explanation of earned value in project management?
Explanation
The budgeted value of the work actually completed — earned value measures progress in the currency of the budget, not in money spent.
Earned value management (EVM) tracks three figures for the same point in time:
- •PV (planned value): the authorized budget for the work scheduled so far
- •EV (earned value): the authorized budget for the work actually completed so far
- •AC (actual cost): the money really spent on the completed work
Comparing them gives the variances and indices: CV = EV − AC, SV = EV − PV, CPI = EV ÷ AC, SPI = EV ÷ PV.
Answer (a)
Why not others:
- •(b) — a time-phased budget for the total cost of the project is the cost baseline (the performance measurement baseline, totalling BAC), not EV
- •(c) — the authorized budget for the planned work is planned value (PV)
- •(d) — the cost actually incurred for the work performed in a period is actual cost (AC)
Key rule: PV is budget for what was planned, EV is budget for what was done, AC is money spent on what was done; EV is the common term in both the cost and the schedule comparison.