ITPEC FE Morning April 2022 Question 55
The arrow diagram below shows a project’s activities and milestones. Which of the following is the minimum project completion time in days?
Explanation
26 days — the minimum completion time is the length of the longest path, the critical path A–E–G–I.
Earliest finish of each activity, starting each one when all activities before it are done:
- •A ends at 3, B at 8, C at 3 + 4 = 7, D at 3 + 7 = 10, E at 3 + 11 = 14
- •F starts after B and C: 8 + 7 = 15
- •G starts after E: 14 + 8 = 22
- •H starts after D, F and, through the dummy, E: 15 + 6 = 21
- •I starts after G and H: 22 + 4 = 26
Answer (d)
Why not others:
- •(a) 20 — the shortest path A–D–H–I; the project ends only when every activity is done, so the longest path decides
- •(b) 24 — A–E–dummy–H–I or A–C–F–H–I, paths with slack
- •(c) 25 — B–F–H–I, the longest path through H, but the E–G branch reaches the start of I one day later than H does
Key rule: "Minimum project duration" means the critical path, the longest path through the network; a dummy adds no time but still passes on a dependency.
Project Management · AI-written, may contain errors