Identify all paths from start to finish:

  • A → E → G → I = 3 + 11 + 8 + 4 = 26
  • A → E → dummy → H → I = 3 + 11 + 0 + 6 + 4 = 24
  • A → D → H → I = 3 + 7 + 6 + 4 = 20
  • A → C → F → H → I = 3 + 4 + 7 + 6 + 4 = 24
  • B → F → H → I = 8 + 7 + 6 + 4 = 25

The longest path is A → E → G → I = 26 days.

Why not others:
- (a) 20 — path A → D → H → I, not the longest

- (b) 24 — paths A → E → dummy → H → I or A → C → F → H → I

- (c) 25 — path B → F → H → I, close but not the maximum

Key rule: Minimum project completion time equals the critical path — the longest path through the network. Dummy activities have zero duration but establish dependencies.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.