ITPEC FE Subject A October 2024 Question 41

Which of the following is an appropriate purpose for using a Work Breakdown Structure (WBS) in a software development project?

Explanation

Hierarchically detail activities into a manageable scale — a WBS is the scope-decomposition tool, not a scheduling or cost tool.

A Work Breakdown Structure splits the whole project scope top-down: deliverables, then sub-deliverables, then work packages. Decomposition stops when each work package is small enough to estimate, assign to one owner and track. Because the WBS covers 100% of the scope, work that is not in it is not in the project.

Answer (b)

Why not others:

  • •(a) — ordering activities and finding the critical path is done with an arrow diagram (PERT/CPM), which takes the WBS activities as its input
  • •(c) — trading duration against cost to minimise total cost is crashing (time-cost trade-off analysis)
  • •(d) — horizontal bars showing start, end and current progress are a Gantt chart

Key rule: WBS answers what work there is, a network diagram answers in what order, a Gantt chart answers when — match the tool to the question it answers.