ITPEC FE Morning April 2021 Question 51
ITPEC FE Morning April 2021 — Question 51 of 80
ISO 21500 Process Groups — identify which activity belongs to which process group.
ISO 21500 defines 5 process groups: Initiating → Planning → Implementing → Controlling → Closing.
- •Initiating — develop project charter, identify stakeholders
- •Planning — define scope, create schedule, plan resources, assess risks
- •Implementing — direct project work, perform quality assurance
- •Controlling — control changes, monitor progress
- •Closing — close project phase, collect lessons learned
Correct answer: (a) To define scope — belongs to the Planning process group.
Why not others:
- (b) To develop a project charter — Initiating, not Planning
- (c) To identify stakeholders — Initiating, not Planning
- (d) To perform quality assurance — Implementing, not Planning
Key rule: Planning answers "what and how" (scope, schedule, budget). Initiating answers "why and who" (charter, stakeholders).
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.