ITPEC FE Morning April 2020 Question 51
Source exam: ITPEC FE Morning April 2020Topic: Project Management
ITPEC FE Morning April 2020 — Question 51 of 80
Scope Creep (PMBOK) — uncontrolled expansion of project/product scope without adjusting time, cost, or resources.
Answer: d)
- •(a) describes a normal change request — scope change with cost/schedule adjustment
- •(b) describes the scope baseline — approved scope statement + WBS + WBS dictionary
- •(c) describes the Control Scope process — monitoring and managing scope changes
- •(d) correct — scope creep is uncontrolled expansion without corresponding adjustments
Key word: "uncontrolled" — changes happen without formal approval or resource adjustment.
AI-generated — may contain errors