ITPEC FE Morning April 2020 Question 51

Topic: Project ManagementAlso asked in October 2024

According to PMBOK, which of the following is the description of scope creep?

Explanation

Uncontrolled expansion of scope without adjusting time, cost and resources — scope creep is growth that bypasses change control.

Scope creep happens when features or work are added informally, such as a user asking for one more report or a developer adding a nice-to-have, without going through the change-control process. The scope grows while the schedule, budget and staffing stay as they were, so the project overruns.

Answer (d)

Why not others:

  • •(a) — a scope change that comes with a matching cost or schedule adjustment is a controlled change request, the opposite of creep
  • •(b) — the approved scope statement, WBS and WBS dictionary together form the scope baseline
  • •(c) — monitoring project and product scope and managing changes to the scope baseline is the Control Scope process, which exists to prevent creep

Key rule: Every scope change should pass through integrated change control with its time and cost impact; growth that skips that step is scope creep.