ITPEC FE Morning October 2020 Question 52

Source exam: ITPEC FE Morning October 2020Topic: Project Management

ITPEC FE Morning October 2020 — Question 52 of 80

Critical Path & Activity Reduction — find the impact of shortening an activity on total project duration.

Identify all paths from start to finish:

  • A → B → E = 6 + 5 + 4 = 15
  • C → D → E = 7 + 5 + 4 = 16critical path
  • C → dummy → F = 7 + 0 + 6 = 13

Original project duration = 16 days (longest path)

After reducing D by 3 days (D = 2):

  • A → B → E = 15
  • C → D → E = 7 + 2 + 4 = 13
  • C → dummy → F = 13

New project duration = 15 days (critical path switches to A → B → E)

Reduction = 16 − 15 = 1 day

Why not others:
- (a) not changed — D was on the critical path, so shortening it does affect duration

- (c) reduced by 2 — would require the new critical path to be 14, but A → B → E = 15

- (d) reduced by 3 — only possible if no other path exceeds 13 days

Key rule: When shortening a critical-path activity, always recheck all paths — a different path may become the new critical path, limiting the actual time saved.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.