Earned Value — Estimate to Complete (ETC) — calculate remaining cost using CPI.
Given:
- BAC = $100,000, AC = $60,000, completion = 40%
- EV = 40% × $100,000 = $40,000
- CPI = EV / AC = 40,000 / 60,000 = 2/3
Remaining work (planned): BAC − EV = $60,000
Since CPI stays the same:
- ETC = (BAC − EV) / CPI = $60,000 / (2/3) = $90,000
Why not others:
- (a) $40,000 — remaining work at planned cost (ignores CPI overrun)
- (b) $60,000 — equals AC spent so far, not remaining cost
- (d) $150,000 — this is EAC (total project cost = AC + ETC), not remaining cost
Key rule: ETC = (BAC − EV) / CPI for remaining cost; EAC = AC + ETC for total cost. The question asks for remaining, so use ETC.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.