ITPEC FE Morning April 2023 Question 54

Source exam: ITPEC FE Morning April 2023Topic: Project Management

ITPEC FE Morning April 2023 — Question 54 of 80

Given: PV = $80,000, AC = $100,000, work is 75% complete.

  • EV = 75% × $80,000 = $60,000
  • SPI = EV / PV = 60,000 / 80,000 = 0.75
  • CPI = EV / AC = 60,000 / 100,000 = 0.6

Answer: (b) — SPI = 0.75, CPI = 0.6

Why not others:
- (a) SPI=0.6, CPI=0.75 — swapped values; SPI uses PV in denominator, CPI uses AC

- (c) SPI=0.75, CPI=1.25 — CPI > 1 would mean under-budget, but actual cost exceeds earned value

- (d) SPI=1.25, CPI=0.75 — SPI > 1 would mean ahead of schedule, but the project is behind

Key rule: EV is always the numerator — SPI = EV/PV, CPI = EV/AC. Values below 1.0 mean behind schedule or over budget.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.