ITPEC FE Morning October 2022 Question 52

Source exam: ITPEC FE Morning October 2022Topic: Project Management

ITPEC FE Morning October 2022 — Question 52 of 80

Responsibility Assignment Matrix (RAM) — maps work packages to the people/roles responsible for them.

RAM (also known as RACI matrix) is a tool for project human resource management that allocates work packages to those who are responsible for project work.

  • R = Responsible (does the work)
  • A = Accountable (approves/owns)
  • C = Consulted (provides input)
  • I = Informed (kept in the loop)

Why not others:
- (b) Defining sponsor's responsibilities — covered by the project charter

- (c) Defining terms of reference — relates to scope statement or charter

- (d) Monitoring stakeholder engagement — that is the stakeholder engagement assessment matrix

Key rule: RAM = "who does what" in a project; maps work packages → people/roles.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.