66 person-months — compute development, add the fixed work, then apply the management overhead to their sum.
- •Development:
500 ÷ 10= 50 person-months - •Installation and education: 10 person-months (given)
- •Subtotal:
50 + 10= 60 - •Project management:
60 × 0.1= 6 - •Total:
60 + 6= 66
Answer (d)
Why not others:
- (b) 60 — stops at the subtotal and forgets the project management overhead entirely
- (c) 65 — applies the 10% to development only (50 × 0.1 = 5), although the question bases it on development plus installation and education
- (a) 51 — adds only 10% of the 10 person-months to the development figure, dropping both the 10 itself and the rest of the overhead
Key rule: Read carefully what the percentage is taken of. Here it is the total of all three activities, so the overhead must be computed last, after the other numbers are summed.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.