ITPEC FE Subject A April 2026 Question 42

Topic: Project ManagementAlso asked in October 2020

The functional size of a new system was estimated to be 500 function points (FPs). Apart from development, the project requires 10 person-months in total for installation of the system and education of developers. Additionally project management requires 10% of the total person-months of development, installation, and education. How many person-months are required in total for this project? Here, the productivity in development is 10 FPs per person-month.

Explanation

66 person-months — compute the development effort, add the fixed work, then add 10% of that sum for management.

  • •Development: 500 ÷ 10 = 50 person-months
  • •Installation and education: 10 person-months (given)
  • •Subtotal: 50 + 10 = 60 person-months
  • •Project management: 60 × 0.1 = 6 person-months
  • •Total: 60 + 6 = 66 person-months

Answer (d)

Why not others:

  • •(b) 60 — stops at the subtotal and leaves out the project management effort
  • •(c) 65 — takes 10% of development only, 50 + 10 + 5, although the question bases it on development, installation and education together
  • •(a) 51 — 50 + 10 × 0.1: development plus 10% of the installation and education work, dropping those 10 person-months themselves

Key rule: Check what a percentage is taken of; an overhead on "the total of" several activities is computed last, after they are summed.

Project Management · AI-written, may contain errors

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.