ITPEC FE Morning April 2018 Question 53

Source exam: ITPEC FE Morning April 2018Topic: Project Management

ITPEC FE Morning April 2018 — Question 53 of 80

Project Stakeholder Definition — identifying who qualifies as a stakeholder per PMBOK

A project stakeholder is any individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project (answer b).

The key distinction is the breadth of this definition — it includes not just active participants but anyone who perceives an impact.

Why not the others:

  • a) describes a project sponsor — provides resources and is accountable for success
  • c) describes a PMO (Project Management Office) — standardizes governance and shares methodologies
  • d) describes a project manager — assigned to lead the team toward project objectives

Key rule: Stakeholder = anyone with a real or perceived interest in the project. The word "perceive" in the definition is the giveaway — sponsors, PMs, and PMOs are all stakeholders, but the definition of stakeholder is the broadest one.

AI-generated — may contain errors