ITPEC FE Morning April 2018 Question 53

According to the PMBOK Guide – Fifth Edition, which of the following is an appropriate definition of a project stakeholder?

Explanation

Anyone who may affect, be affected by, or perceive itself to be affected by the project — the PMBOK Guide defines a stakeholder this broadly.

Stakeholders include people inside the project (sponsor, project manager, team, PMO) and outside it (customers, users, suppliers, regulators, the public). The word "perceive" matters: a group that only believes it is affected, and may resist the project, is still a stakeholder to identify and manage.

Answer (b)

Why not others:

  • •(a) — describes the project sponsor, who provides resources and support and is accountable for enabling success
  • •(c) — describes the project management office (PMO), which standardizes governance and shares resources, methodologies, tools and techniques
  • •(d) — describes the project manager, assigned by the performing organization to lead the team

Key rule: The sponsor, the PMO and the project manager are each a stakeholder, but the definition of stakeholder is the broad one: anyone who affects or is affected by the project, really or in their own view.

Project Management · AI-written, may contain errors

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official FE past-paper collection or Report an issue.