Project Management

Project Management

66 questions · IT Passport · 51–66

Practice

After the detailed design of an information system is complete, it is decided to outsource programming to an outsourcing contractor with clearly defined specifications, deliverables, and scope of work. Which of the following is the most appropriate management activity of the project manager of the ordering company?

Which of the following is the most appropriate case where project management methods are applied?

In a system development project, the installation of PCs for development is delayed. However, a plan was created beforehand to use old PCs as an alternative in the case of a delay, so it is possible to start the development activities according to the plan. In this case, which of the following is implemented as project management?

Which of the following is the most appropriate description concerning risk management in a project?

The development of 50 programs is outsourced either to Company A or Company B. Which of the following is the combination of a company with a short development period and a company with a low development cost?

[Assumptions]• Company AProductivity: Creation of one (1) program in two (2) days Cost: 40,000 yen/day• Company BProductivity: Creation of one (1) program in three (3) days Cost: 30,000 yen/day
• One (1) program is created at a time in a sequence
OptionShort development periodLow development cost

Which of the following items must be clarified in order to determine the appropriate assignment of the project members?

Which of the following is an appropriate description of WBS creation in project management?

Knowledge areas in project management include project cost management, project human resource management, project time management, and project quality management. In project quality management of system development, which of the following is an appropriate activity for quantitatively analyzing the quality of deliverables?

At the request of a user department, the development department launches a project of system development. Which of the following is the most appropriate role of the project manager?

The project management knowledge areas include project cost management, project human resource management, project time management, and project procurement management. In a system development project, which of the following is an appropriate activity of project procurement management when a device is purchased for testing?

When the progress of a project is managed, which of the following is an appropriate item to be considered?

Which of the following is the first task to be performed when a project is initiated?

In the arrow diagram below, what is the maximum number of days that can be allowed as a delay of the activity “C→F” on condition that the total number of days required for activities from A through G is not affected?

ABCDEFG3374366474
[Legend]Number ofdays required

In a system development project, as a measure for improving the productivity of program creation, a training to improve skills for using development tools is planned for new members. Which of the following is the most appropriate indicator to evaluate the effect of this measure?

Which of the following is an appropriate explanation of component decomposition that is performed to create the WBS of a system development project?

The table below shows the relationship between the standard number of staff and the number of days required to complete preparation activities A through E of an event. The preparation activities started 35 days before the event and have been conducted according to the table; however, only one staff member was assigned during the first 20 days. In order to complete the remaining activities to meet the original deadline, what is the minimum number of staff members that must be reserved per day for the remaining period? Here, the preparation activities can be performed in any sequence, any staff member can achieve the same productivity in each activity, and any number of staff members can be assigned to an activity at one time.

Preparation activityStandard number of staff(persons)Number of days required(days)
A25
B25
C310
D25
E510