After the detailed design of an information system is complete, it is decided to outsource programming to an outsourcing contractor with clearly defined specifications, deliverables, and scope of work. Which of the following is the most appropriate management activity of the project manager of the ordering company?
Which of the following is the most appropriate case where project management methods are applied?
In a system development project, the installation of PCs for development is delayed. However, a plan was created beforehand to use old PCs as an alternative in the case of a delay, so it is possible to start the development activities according to the plan. In this case, which of the following is implemented as project management?
Which of the following is the most appropriate description concerning risk management in a project?
The development of 50 programs is outsourced either to Company A or Company B. Which of the following is the combination of a company with a short development period and a company with a low development cost?
Which of the following items must be clarified in order to determine the appropriate assignment of the project members?
Which of the following is an appropriate description of WBS creation in project management?
Knowledge areas in project management include project cost management, project human resource management, project time management, and project quality management. In project quality management of system development, which of the following is an appropriate activity for quantitatively analyzing the quality of deliverables?
At the request of a user department, the development department launches a project of system development. Which of the following is the most appropriate role of the project manager?
The project management knowledge areas include project cost management, project human resource management, project time management, and project procurement management. In a system development project, which of the following is an appropriate activity of project procurement management when a device is purchased for testing?
When the progress of a project is managed, which of the following is an appropriate item to be considered?
Which of the following is the first task to be performed when a project is initiated?
In the arrow diagram below, what is the maximum number of days that can be allowed as a delay of the activity “C→F” on condition that the total number of days required for activities from A through G is not affected?
In a system development project, as a measure for improving the productivity of program creation, a training to improve skills for using development tools is planned for new members. Which of the following is the most appropriate indicator to evaluate the effect of this measure?
Which of the following is an appropriate explanation of component decomposition that is performed to create the WBS of a system development project?
The table below shows the relationship between the standard number of staff and the number of days required to complete preparation activities A through E of an event. The preparation activities started 35 days before the event and have been conducted according to the table; however, only one staff member was assigned during the first 20 days. In order to complete the remaining activities to meet the original deadline, what is the minimum number of staff members that must be reserved per day for the remaining period? Here, the preparation activities can be performed in any sequence, any staff member can achieve the same productivity in each activity, and any number of staff members can be assigned to an activity at one time.
Mr. A is doing the work of the planning phase of a new project, and has started estimating the development cost. Which of the following is the most appropriate method for estimating the approximate cost in a short time at this phase?
Which of the following is the most appropriate explanation of WBS in project management of system development?
In a project, which of the following is an appropriate document that formally authorizes a new project?
Which of the following is the most appropriate description concerning project meetings held in a system development project?
When the activities in the following table are performed by 3 persons, what is the minimum number of days required to complete all activities? Here, an activity that requires multiple staff cannot be started until all of them are available, and assigning more staff than the specified number does not shorten the days required. Also, an activity that has been started cannot be interrupted until it is completed.
Which of the following is the most appropriate description of the case where a change request has arisen in a project in which a change control board has been established?
Among the techniques used in a system development project, which of the following lists all and only the appropriate techniques used for creating a schedule?
There is a project to create 100 programs in 40 days with a budget of 20 million yen at the time of planning. At the point when 20 days of the project have passed, 40 programs, which are 40% of the whole, have been completed, and a cost of 10 million yen has been incurred. When the indicators of the project are calculated with the following evaluation formulas, which of the following is the appropriate combination of the indicators of the project? Here, the number of days and the cost required for creating each program are all the same, and the same amount of work is always performed during the project period.
[Evaluation formulas]
Schedule (%):
(Number of completed programs ÷ Number of programs expected to be completed at the time of evaluation) × 100
Cost (%):
(Cost incurred for the completed programs
÷ Cost planned for the completed programs) × 100
Which of the following lists all and only the appropriate items as the targets of the scope of a system development project entrusted by a customer?
At the start of a system development project, it was decided to prepare a plan concerning human resources. In this plan, which of the following lists all and only the appropriate items that should be considered in order to assign personnel appropriately and obtain better performance?
Which of the following lists all and only the appropriate examples that correspond to a project?
Which of the following is the most appropriate activity performed in project integration management when a system development project is closed?
The relationships between the activities of a project and their required times are shown in an arrow diagram. Among the four (4) nodes B through E in this arrow diagram, which of the following is the node at which the start of all the activities that begin from that node can be delayed the most without affecting the completion time of the entire process? Here, an activity that begins from a node cannot start until all the activities that lead to that node are completed, and the setup time from one activity to the next activity is not considered.
Cost estimation methods in a software development project include the bottom-up method, the function point method, and the analogous estimation method. Which of the following is the appropriate combination of the methods used in estimation and the descriptions A through C concerning their characteristics?
In a system development project, which of the following is an appropriate activity that is performed in project scope management after a request for the addition of a new function has been approved by the change control board?
As a result of performing activities based on the following arrow diagram, activity D was delayed by 2 days, and activity F was completed 3 days ahead of schedule. How much did the number of days required for the entire set of activities change compared with the plan?
In project management, it is required to balance competing constraints such as schedule, cost, and quality. Which of the following is an appropriate response when it has been decided to shorten the planned development schedule?
In the arrow diagram in the figure, activity B was completed 2 days late. Therefore, in order to complete all the activities within the scheduled period, it was decided to add personnel to activity D. When 20 personnel are initially assigned to activity D, what is the minimum number of personnel that need to be added to activity D? Here, the work efficiency of the personnel is uniform.
Software of 120 k steps was developed. When the actual productivity in each process of the development is as shown in the table, how many person-months is the effort for the entire development? Here, productivity is the number of k steps per person-month.
Unit: k steps/person-month
In a system development project, it was decided to additionally create a program in order to respond to a request from users. In order to create this program, it was decided to assign a programmer who had finished creating the preceding programs. Then, the schedule was changed so that all of the programs could be created by the planned start date of the integration test, and the new plan was made known within the project. Which of the following is the activity that manages change requests in this way?
In a system development project, which of the following is the project management activity that compares the list of screens and forms defined as deliverables with the number of screens and forms actually created, and confirms the differences that arose during development and their reasons?
When a WBS is created, a supplementary document that describes the description of the work, the completion criteria, and other such information is created. Which of the following is an appropriate purpose of this document?
Activities in project management include project integration management, project scope management, project schedule management, project cost management, and the like. Activities in project integration management include determining resource allocation and coordinating trade-offs between competing objectives and alternatives. In a system development project, which of the following is an appropriate activity in project integration management when a function that is not in the initial plan is to be added?
Which of the following is an appropriate measure for clarifying the rules of communication among project members?
In examining the goals and other such matters of a project, which of the following is the technique that divides the results of ideas put forward by a group into groups and organizes them systematically?
In a system development project, there is a risk that the completion of the test process is delayed because the delivery of the PCs used in the test process is delayed, and countermeasures were decided. When risk responses are classified into the four (4) categories of avoidance, mitigation, acceptance, and transfer, which of the following is the most appropriate description that corresponds to acceptance?
What are the shortest required days and the longest required days of the process in the figure?