IPA IP 2022 Question 50
A question IPA Japan published in 令和4年度 ITパスポート試験 公開問題 問50, translated into English. ITPEC is based on the same exams.
Software of 120 k steps was developed. When the actual productivity in each process of the development is as shown in the table, how many person-months is the effort for the entire development? Here, productivity is the number of k steps per person-month.
Unit: k steps/person-month
Explanation
50 person-months — each process has to handle all 120 k steps at its own productivity, so compute the effort for each process and add them.
Effort = size ÷ productivity:
- •Design: 120 ÷ 6.0 = 20 person-months
- •Production: 120 ÷ 4.0 = 30 person-months
- •Total: 20 + 30 = 50 person-months
Answer (d)
Why not others:
- •(a) 10 — less than the design process alone needs, 120 ÷ 6.0 = 20 person-months
- •(b) 12 — divides by the summed productivity, 120 ÷ 10 = 12, as though the two processes shared the work instead of each covering all 120 k steps
- •(c) 24 — divides the size once by the average productivity, 120 ÷ 5.0 = 24, counting the 120 k steps for one process instead of for each
Key rule: Productivity is per process: divide the whole size by each process's productivity and add the efforts; never add or average the productivities themselves.