ITPEC IP April 2020 Question 56

Which of the following is the most appropriate case where project management methods are applied?

Explanation

Applied when a team is created to construct a system — project management fits work that is temporary and aims at a specific result.

Building a system has a goal, a start and an end, a budget and a team assembled for it. Project management methods (WBS, scheduling, cost and quality control, risk management) exist to plan and control exactly this kind of one-off undertaking until the goal is reached.

Answer (d)

Why not others:

  • •(a) — routine operation of a computer system is continuing, repeated work, handled by operations and service management, not as a project
  • •(b) — standards for setting prices when work is outsourced are procurement and contract rules; they are not a way of running a project
  • •(c) — defining the roles of a permanent department is organizational design; a department continues indefinitely, unlike a project

Key rule: Use project management for a temporary effort with a specific goal; ongoing, repeated work is operations and is managed differently.

Project Management · AI-written, may contain errors

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.