The ordering company's project manager should request periodic progress reports and verify the quality of the completed program. With clearly defined deliverables and scope, the customer manages the contract through outcomes, progress, and acceptance rather than directly supervising the contractor's personnel.

Answer (a)

Why not others:
- replacing individual contractor staff or managing their attendance intrudes into the contractor's personnel management

- specification changes should follow formal contract and change-control channels, not direct orders to contractor employees

Key rule: In deliverable-based outsourcing, the customer controls agreed scope, progress, quality, and acceptance while the supplier manages how its staff perform the work.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.