IPA IP 2024 Question 49

A question IPA Japan published in 令和6年度 ITパスポート試験 公開問題 問49, translated into English. ITPEC is based on the same exams.

Cost estimation methods in a software development project include the bottom-up method, the function point method, and the analogous estimation method. Which of the following is the appropriate combination of the methods used in estimation and the descriptions A through C concerning their characteristics?

AThe individual activities required for the project are identified, and the person-hours for each activity are estimated and totaled.BIt is a method used in the initial stage of a project, and the cost is estimated by making use of past cases.CFocusing on data input/output and functions, the software size is estimated, and the cost is estimated by multiplying it by a coefficient, etc.
OptionBottom-up methodFunction point methodAnalogous estimation method

Explanation

Bottom-up: A, function point: C, analogous: B — match each estimation method to how it arrives at the cost.

  • •Bottom-up method — break the project into its individual activities (a WBS), estimate the person-hours of each and add them up: A
  • •Function point method — count the functions seen from outside (inputs, outputs, files, inquiries), weight them by complexity to get the software size, then convert it to effort and cost with coefficients: C
  • •Analogous estimation method — compare with the actual results of similar past projects; quick and usable in the early stage when details are not yet known: B

Answer (a)

Why not others:

  • •(b) — gives the bottom-up method the past cases of B, which is analogous estimation, and the function point method the activity totals of A
  • •(c) and (d) — give the bottom-up method C: measuring size from data input/output and functions is the function point method, not a sum of activities

Key rule: Bottom-up adds up activities, the function point method measures functions to get size, and analogous estimation leans on similar past projects (early, rough).