ITPEC IP October 2020 Question 55
The development of 50 programs is outsourced either to Company A or Company B. Which of the following is the combination of a company with a short development period and a company with a low development cost?
Explanation
Company A for both — A finishes sooner and, over the whole job, also costs less despite its higher daily rate.
Programs are created one at a time, so the period is the number of programs times the days per program, and the cost is that period times the daily rate:
Per program, A costs 2 × 40000 = 80000 yen and B 3 × 30000 = 90000 yen, so A is cheaper whatever the number of programs.
Answer (a)
Why not others:
- •(b) — picks B as cheaper by comparing only the daily rates, 30,000 against 40,000 yen, and ignoring that B needs 50 more days
- •(c) — reverses both: B takes 50 days longer and costs 500,000 yen more
- •(d) — B is cheaper per day but slower, so it is neither faster nor cheaper overall
Key rule: Compare total cost, not the daily rate: cost = days needed × rate per day, so a faster supplier with a higher rate can still be cheaper overall.