ITPEC IP October 2020 Question 55

The development of 50 programs is outsourced either to Company A or Company B. Which of the following is the combination of a company with a short development period and a company with a low development cost?

[Assumptions]• Company AProductivity: Creation of one (1) program in two (2) days Cost: 40,000 yen/day• Company BProductivity: Creation of one (1) program in three (3) days Cost: 30,000 yen/day
• One (1) program is created at a time in a sequence
OptionShort development periodLow development cost

Explanation

Company A for both — A finishes sooner and, over the whole job, also costs less despite its higher daily rate.

Programs are created one at a time, so the period is the number of programs times the days per program, and the cost is that period times the daily rate:

CompanyDevelopment periodDevelopment cost
A50 × 2 = 100 days100 × 40000 = 4000000 yen
B50 × 3 = 150 days150 × 30000 = 4500000 yen

Per program, A costs 2 × 40000 = 80000 yen and B 3 × 30000 = 90000 yen, so A is cheaper whatever the number of programs.

Answer (a)

Why not others:

  • •(b) — picks B as cheaper by comparing only the daily rates, 30,000 against 40,000 yen, and ignoring that B needs 50 more days
  • •(c) — reverses both: B takes 50 days longer and costs 500,000 yen more
  • •(d) — B is cheaper per day but slower, so it is neither faster nor cheaper overall

Key rule: Compare total cost, not the daily rate: cost = days needed × rate per day, so a faster supplier with a higher rate can still be cheaper overall.