ITPEC IP October 2020 Question 55

Source exam: ITPEC IP October 2020Topic: Project Management

ITPEC IP October 2020 — Question 55 of 100

Company A provides both the shorter development period and the lower total cost. For 50 sequential programs, A needs 50 × 2 = 100 days and costs 100 × 40,000 = 4,000,000 yen. B needs 150 days and costs 150 × 30,000 = 4,500,000 yen.

Answer (a)

Why not others:
- B's daily rate is lower, but each program takes an extra day

- total cost depends on daily rate multiplied by total days, not daily rate alone

- therefore the other combinations incorrectly assign at least one advantage

Key rule: Compare duration from productivity first, then calculate total cost using duration × cost per day.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.