ITPEC IP April 2018 Question 55

Source exam: ITPEC IP April 2018Topic: Project Management

ITPEC IP April 2018 — Question 55 of 100

Presenting device specifications to candidate suppliers, evaluating proposals, and selecting the supplier is procurement management. It covers obtaining products or services from outside the project organization, including solicitation, source selection, contracting, and supplier control.

Answer (d)

Why not others:
- scheduling testing after delivery belongs to time or schedule management

- training the tester belongs to human resource development

- adding and tracking purchase cost belongs to cost management

Key rule: Procurement management defines what to buy, requests supplier offers, selects and contracts with a source, and manages the resulting agreement.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.