The project manager monitors progress and takes preventive or corrective measures when problems or deviations threaten the plan. This role integrates scope, schedule, cost, quality, resources, communication, and risk so that objectives can be achieved.

Answer (a)

Why not others:
- the user department should state its business need and project request

- system requirements are elicited and agreed with users, not simply presented to them as their own requirements

- raising organizational funds is a sponsor or management responsibility

Key rule: The project manager plans, coordinates, monitors, and controls project work; the sponsor provides authority and funding, and users own business needs.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.