ITPEC IP October 2018 Question 51
ITPEC IP October 2018 — Question 51 of 100
The project goals must be clarified first. The goals establish the intended outcomes, scope direction, and success criteria. Only after stakeholders agree on what the project is meant to achieve can the team create a meaningful schedule and budget or monitor progress against a baseline.
Answer (c)
Why not others:
- progress management requires an approved plan and work already underway
- scheduling depends on known objectives, scope, and required work
- budget planning depends on the resources and work needed to reach the goals
Key rule: Define why the project exists and what success means before planning when, how, and at what cost the work will be performed.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.