ITPEC IP October 2022 Question 52
ITPEC IP October 2022 — Question 52 of 100
A WBS hierarchically decomposes all project work into manageable units. The Work Breakdown Structure divides deliverables and activities into progressively smaller components until work packages can be estimated, assigned, scheduled, and controlled.
Answer (d)
Why not others:
- CRM manages customer relationships
- ERP integrates enterprise resources and processes
- PPM analyzes and manages a portfolio of products or projects
Key rule: WBS answers what work is included in the project and establishes the work packages used for planning and control.