ITPEC IP April 2021 Question 57

Source exam: ITPEC IP April 2021Topic: Project Management

ITPEC IP April 2021 — Question 57 of 100

A WBS identifies all project work and organizes it hierarchically into manageable units. The Work Breakdown Structure decomposes deliverables and activities until work packages can be estimated, assigned, scheduled, budgeted, and controlled.

Answer (d)

Why not others:
- CRM manages customer relationships

- ERP integrates enterprise resources and business processes

- PPM supports product or project portfolio evaluation and resource allocation

Key rule: WBS is the project-planning tool that decomposes total scope into controlled work packages.