ITPEC IP April 2025 Question 55

Source exam: ITPEC IP April 2025Topic: Project Management

ITPEC IP April 2025 — Question 55 of 100

WBS — a Work Breakdown Structure decomposes the project's total scope into a hierarchy of manageable work.

The project deliverables and activities are successively divided into smaller components until work packages can be estimated, assigned, scheduled, and controlled. The hierarchy helps ensure that all required work, and only required work, is represented.

Answer (d)

Why not others:
- (a) CRM manages customer relationships and related information

- (b) ERP integrates enterprise resources and business processes

- (c) PPM manages and evaluates a portfolio of projects

Key rule: WBS organizes the scope of one project hierarchically; schedules and budgets are then built from its work packages.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.