Evaluation standards should be prepared before selecting a supplier. They define consistent criteria, weights, evidence, and scoring for comparing proposals on capability, quality, cost, schedule, risk, and contractual conditions.

Answer (c)

Why not others:
- a communication plan governs project information exchange

- test cases verify a delivered product

- a project charter authorizes the project and states high-level objectives

Key rule: Supplier selection requires predefined, objective evaluation criteria so competing offers are assessed fairly and consistently.