ITPEC IP October 2019 Question 57

Source exam: ITPEC IP October 2019Topic: Project Management

ITPEC IP October 2019 — Question 57 of 100

A work breakdown structure (WBS) identifies the project's work and decomposes it into a hierarchical structure of manageable units. Successive levels divide deliverables and work into smaller components until work packages can be estimated, assigned, scheduled, and controlled.

Answer (d)

Why not others:
- CRM manages relationships and interactions with customers

- ERP integrates an organization's business resources and processes

- PPM manages and prioritizes a portfolio of multiple projects

Key rule: A WBS hierarchically decomposes the total project scope into clearly defined, manageable work packages.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.