ITPEC IP April 2026 Question 54

Source exam: ITPEC IP April 2026Topic: Project Management

ITPEC IP April 2026 — Question 54 of 100

Impact of an activity delay on the entire schedule — progress management controls actual timing against the plan.

It tracks start/finish status, dependencies, milestones, critical-path effects, and corrective action. A delayed critical activity can move the project completion date, while a delay with float may not.

Answer (c)

Why not others: (a) test coverage and (d) review procedures belong to quality management; (b) forecast cost increase belongs to cost management.

Key rule: Progress management asks whether work is on schedule; quality management asks whether outputs meet standards; cost management asks whether spending meets budget.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.