ITPEC IP April 2021 Question 56
ITPEC IP April 2021 — Question 56 of 100
Progress management evaluates how an activity's delay affects the overall schedule. It compares actual progress with the plan, examines dependencies and critical paths, forecasts completion, and determines whether corrective scheduling action is necessary.
Answer (c)
Why not others:
- test completeness is a quality-management concern
- expected future cost growth belongs to cost management
- establishing design-review procedures is quality planning and assurance
Key rule: Progress management controls time and schedule status; quality and cost are managed through their respective disciplines.