ITPEC IP October 2019 Question 54

Source exam: ITPEC IP October 2019Topic: Project Management

ITPEC IP October 2019 — Question 54 of 100

Progress management must determine how a delayed activity affects the schedule of the entire project. A delay may or may not postpone completion depending on dependencies, available float, and whether the activity lies on the critical path, so its overall schedule impact must be assessed.

Answer (c)

Why not others:
- checking whether integration testing is sufficiently comprehensive concerns quality

- forecasting a future cost increase concerns cost management

- establishing a design-review procedure for finding defects also concerns quality management

Key rule: Progress management compares actual and planned timing and evaluates how activity delays affect milestones and project completion.

AI-generated — may contain errors