Progress management checks how an activity delay affects the overall schedule. It compares actual and planned dates, analyzes dependencies and float, identifies effects on milestones or the critical path, and supports corrective actions such as resequencing or reallocating resources.
Answer (c)
Why not others:
- (a) test completeness from multiple viewpoints is a quality-management concern
- (b) projected cost increase belongs to cost management
- (d) establishing design-review procedures for defect detection belongs to quality planning and management
Key rule: Progress management controls time and schedule; quality management controls conformance and defect prevention, while cost management controls expenditure and forecasts.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.