ITPEC IP April 2026 Question 55
ITPEC IP April 2026 — Question 55 of 100
An aggregate schedule of the entire project's main deliverables and activities — this is the master schedule.
It provides a high-level view from requirements through implementation, showing major phases, milestones, and deliverables. Detailed weekly, daily, or process schedules are derived beneath it.
Answer (d)
Why not others: (a) is a short-term weekly schedule; (b) is a detailed daily work schedule; (c) is more detailed and limited to main-process activities rather than the whole project overview.
Key rule: A master schedule is broad and project-wide; lower-level schedules progressively add activity and resource detail.