ITPEC IP April 2023 Question 55
ITPEC IP April 2023 — Question 55 of 100
The leader should have the team analyze concrete measures against quality loss and build project consensus. Omitting work merely to recover schedule can introduce unacceptable defects or rework. The team should examine impacts, alternatives, quality criteria, and authorized trade-offs so the response protects required quality while addressing delay.
Answer (a)
Why not others:
- (b) a vote by selected skilled members does not replace evidence-based impact analysis and stakeholder agreement
- (c) experience alone does not make the leader's proposal correct
- (d) replacing dissenting members suppresses valid quality concerns and harms teamwork
Key rule: Resolve project conflict by analyzing facts and constraints, developing alternatives, and reaching accountable agreement on an authorized plan.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.