ITPEC IP October 2019 Question 56
ITPEC IP October 2019 — Question 56 of 100
Integration management compares the added staff and cost with the number of schedule days that can be saved. Advancing delivery affects several management areas simultaneously, so the decision must balance schedule improvement against resource and cost consequences.
Answer (b)
Why not others:
- changing task sequence considers only the schedule structure
- estimating only the cost impact does not integrate the schedule benefit
- revising only staff assignment focuses on human resource management
Key rule: Project integration management coordinates trade-offs across scope, schedule, cost, resources, quality, and risk before approving a project-wide change.
AI-generated — may contain errors
The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.