ITPEC IP October 2019 Question 53

Source exam: ITPEC IP October 2019Topic: Project Management

ITPEC IP October 2019 — Question 53 of 100

Project integration management creates the project management plan that coordinates execution, monitoring, and control of the entire project. It combines the subsidiary plans for scope, schedule, cost, quality, resources, and other areas into one coherent basis for managing the work.

Answer (d)

Why not others:
- the development schedule is primarily an output of schedule management

- the list of deliverables is defined through scope management

- the project budget is developed through cost management

Key rule: Integration management unifies all project management areas and maintains the overall project management plan.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.