ITPEC IP October 2019 Question 53
ITPEC IP October 2019 — Question 53 of 100
Project integration management creates the project management plan that coordinates execution, monitoring, and control of the entire project. It combines the subsidiary plans for scope, schedule, cost, quality, resources, and other areas into one coherent basis for managing the work.
Answer (d)
Why not others:
- the development schedule is primarily an output of schedule management
- the list of deliverables is defined through scope management
- the project budget is developed through cost management
Key rule: Integration management unifies all project management areas and maintains the overall project management plan.
AI-generated — may contain errors