ITPEC IP April 2026 Question 67

Source exam: ITPEC IP April 2026Topic: Corporate Activities

ITPEC IP April 2026 — Question 67 of 100

C → A → B — Johnson's rule places the job with the smallest time on X first and the job with the smallest time on Y last.

The overall smallest time is B's 5 minutes on Y, so B goes last. Among A and C, the smallest is C's 6 minutes on X, so C goes first, leaving A in the middle. Schedule: C uses X 0–6, Y 6–14; A uses X 6–14, Y 14–24; B uses X 14–24, Y 24–29. Completion is 29 minutes.

Answer (c)

Why not others: The other sequences create longer idle waits on Y or place B before the end despite its shortest time being on the second machine.

Key rule: For two-machine flow shops, smallest time on the first machine goes early; smallest time on the second goes late.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.