ITPEC IP October 2019 — Question 66 of 100
The minimum-completion sequence is C → A → B, with a makespan of 29 minutes. On machine X, C, A, and B finish at minutes 6, 14, and 24. On machine Y, they run at 6–14, 14–24, and 24–29, so Y has no idle gap after work begins. The other listed sequences finish in 32, 31, and 34 minutes respectively.
Answer (c)
Why not others:
- A → B → C finishes at minute 32
- A → C → B finishes at minute 31
- C → B → A finishes at minute 34
Key rule: For each job on the second machine, start time is the later of its first-machine completion and the second machine's previous completion.