ITPEC IP April 2024 Question 67
There are activities A, B, and C that use machines X and Y, and it is required in each activity that the machines are used in the sequence of machine X, machine Y. When the use times of machines X and Y in each activity are as shown in the table below, which of the following is the sequence of the activities where the total time required to complete the three (3) activities becomes minimum? Here, machines X and Y can be used in parallel as shown in the figure below, but two (2) or more tasks cannot be performed simultaneously with any machine and the sequence of activities must be the same for both machines.
Table Use times of machines X and Y in each activity
Figure Schedule of using the machines (Example of when activities are performed in the sequence A → B → C)
Explanation
C → A → B — start with the activity that frees machine X soonest and end with the one that is shortest on machine Y.
Johnson's rule: take the smallest time in the table; if it is on X, schedule that activity first, if on Y, last; repeat with the rest. The smallest is B on Y (5 minutes), so B goes last; of A and C the smallest is C on X (6 minutes), so C goes first. Tracing each order (Y starts an activity when X has finished it and Y is free):
For C → A → B: X runs C 0–6, A 6–14, B 14–24; Y runs C 6–14, A 14–24, B 24–29. Y never waits after starting: 6 + 23 = 29 minutes.
Answer (c)
Why not others:
- •(a) A → B → C — the example in the figure; Y waits 8 minutes for A to start and again between B and C, finishing at 32
- •(b) A → C → B — no gaps once Y starts, but starting with A's 8 minutes on X instead of C's 6 delays Y by 2 minutes, finishing at 31
- •(d) C → B → A — Y waits for B and then for A, and A's 10 minutes on Y come last, finishing at 34
Key rule: In two-machine scheduling, keep the second machine busy: the first job should be short on the first machine, and the last job short on the second machine.
Corporate Activities · AI-written, may contain errors
This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.