ITPEC IP April 2024 Question 55

Source exam: ITPEC IP April 2024Topic: Project Management

ITPEC IP April 2024 — Question 55 of 100

A master schedule summarizes the major deliverables and activities across the entire project. It provides a high-level view from requirements definition through installation, showing major phases, milestones, dependencies, and target dates. Detailed weekly, daily, or task-level schedules can then be derived and managed beneath this overall framework.

Answer (d)

Why not others:
- (a) a one-week detailed schedule is short-term and operational

- (b) a one-day timetable with individual owners is much more detailed than a master schedule

- (c) detailed descriptions of activities in main processes belong to lower-level schedules or work plans

Key rule: The master schedule is the project-wide summary; detailed schedules progressively decompose its phases and milestones into executable tasks.

AI-generated — may contain errors