ITPEC IP October 2020 Question 56

Source exam: ITPEC IP October 2020Topic: Project Management

ITPEC IP October 2020 — Question 56 of 100

A master schedule summarizes the main deliverables and activities across the entire project. It provides the high-level timeline, major phases, milestones, dependencies, and target completion points from requirements through installation.

Answer (d)

Why not others:
- a one-week detailed plan is a short-term or detailed schedule

- an hourly daily plan is an operational work schedule

- detailed activities within main processes belong to lower-level schedules rather than the project master view

Key rule: The master schedule is the top-level integrated timeline; detailed schedules progressively decompose its phases and milestones.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.