Incident management restores normal service as quickly as possible and minimizes business impact — rapid recovery is prioritized over finding the underlying cause.

An incident is an unplanned interruption or degradation of an IT service. The process records, categorizes, prioritizes, diagnoses, escalates, resolves, and closes incidents so users regain service promptly.

Answer (c)

Why not others:
- (a) migration of new software into production belongs to release and deployment management

- (b) handling change requests belongs to change management

- (d) maintaining information about service components and relationships belongs to configuration management

Key rule: Incident management restores service; problem management seeks root causes, change management controls modifications, and configuration management maintains component records.

AI-generated — may contain errors

The original exam layout is preserved in the image so diagrams, formulas, tables, and code remain accurate.

This question comes from an official ITPEC past paper. ITPEC Practice is an independent study tool and is not affiliated with ITPEC. See the official IP past-paper collection or Report an issue.